Smokestack / Chimney Old Saskatchewan Hospital, North Battleford, SK

April 2021 is when the crew commenced salvage and final demolition on the Smokestack/Chimney.
The Smokestack/Chimney on the Project was 170 feet in height. We removed the top decorative brick for salvage and was packaged and delivered to the Historical Society in North Battleford, SK. Another section of brick was removed for salvage to be maintained by the Historical Society of North Battleford.
Our company will donate a couple of truck loads of brick from the Old Saskatchewan Hospital to the Western Development Museum in North Battleford, SK for them to create something to commemorate that structure.
April 23, 2021 we utilized our high reach and demolished the remaining smokestack/chimney that morning.

Old Saskatchewan Hospital Project, Industrial Therapy & EMO Structures – North Battleford, SK

The Old Saskatchewan Hospital structures:

  • Corrections Centre
  • Quonset
  • Maintenance Building
  • Cottages
  • Greenhouse
  • Industrial Therapy
  • EMO
  • Gymnasium
  • Main Hospital

This Project had our crew operating many types of equipment, materials were recycled when possible with other materials sent to various approved disposal sites due to the hazardous materials to be managed as per environmental requirements.

99% of material diverted from landfill as we were able to recycle the materials from the demolition Project.

Old Saskatchewan Hospital Project, Corrections Centre – North Battleford, SK

The Old Saskatchewan Hospital structures:

  • Corrections Centre
  • Quonset
  • Maintenance Building
  • Cottages
  • Greenhouse
  • Industrial Therapy
  • EMO
  • Gymnasium
  • Main Hospital

This Project had our crew operating many types of equipment, materials were recycled when possible with other materials sent to various approved disposal sites due to the hazardous materials to be managed as per environmental requirements.

99% of material diverted from landfill as we were able to recycle the materials from the demolition Project.